SAUDI ARABIA
Haradh-3 Now 70% Complete, Says Saudi Aramco
The construction phase of the Haradh Arab Light Crude Increment-3 project is now 70% complete, with all the major process equipment installed, about 1,090 tons of structure steel erected and more than 3,100 tons of steel piping materials received, Saudi Aramco said on 7 September (MEES, 18 April). The company has installed the High Pressure Production Trap at the Haradh GOSP-3...