Fast-Tracked Khursaniyah Project On Track For December 2007 Start-Up

Saudi Aramcos fast-track approach to the Khursaniyah project has cut 20 months of preliminary design work to eight months with the result that first concrete for the producing facility was poured on 12 September, according to a company statement. The Khursaniyah project, entailing work to bring back into production the three mothballed fields Khursaniyah,...