VOL. XLVII

No 06

09-February-2004

IRAN

South Pars Platforms Completed By Irans Sadra

Two wellhead platform topsides for Phases 4 and 5 of the South Pars gasfield development offshore Iran have been completed by Iranian engineering contractor Sadra. Sadra Managing Director Mohammad Banaei was quoted by the IRNA news agency on 15 January as saying that the two topsides were now ready for installation. Each weighed about 4,800 tons. The two were built at a combined cost of $93mn. The topsides will be...