ALGERIA

In Salah Production Tests Underway With First Gas Now Seen In Early June

BP, Statoil and Sonatrach have started production testing from the Krechba and Teg gasfields in the run up to first gas from the $2.7bn In Salah project in early June several months ahead of schedule, MEES learns. Pipeline testing at the development has been underway for two months and MEES understands that small amounts of gas are already being processed at the Krechba central production...