Egypt Commissions 650MW Power Plant In Sinai

Egypts new power plant at 'Uyun Musa in the Sinai Desert, which has been under construction since 1997 by Germanys Siemens, has now been commissioned after the completion of successful tests on the plants two 325mw steam turbine generators (MEES, 6 July 1998 and 10 May 1999). The new facility was constructed by Siemens under a contract concluded with the Egyptian Electricity Authority (EEA) prior to the adoption of...